INDUSTRIAL DEV PHASE II

SINGAPORE 

MIXED USE DEVELOPMENT

www.syscon.com.sg

Brief:

Effectively manage the maximisation and use of undeveloped land to compliment the current operations of the business

Execution:

Management and Construction of a 700,000 Square Feet Manufacturing Facility with Ancillary Office and Multi Storey Above Ground Car park The challenge here was to build entirely out of precast and to design in a manner with triple use of space. Fire Control systems needed to go through rigorous simulations to minimise need for costly fittings throughout project . Project was completed early and surpassed expectations for performance

CREDITS.

CONSTRUCTION TIMELINE

22 Months 

Scope of Construction

Ground Works . Piling . Above Ground Works and Heavy Machinery Installment

Milestone

Project Was Completed Ahead of Schedule

Much Like the1st Phase , Entire Development was built using Concrete Precast Components 

Main challenges involved piling and pile cap works which were oversized to accomodate the multi-storey 20 KN loading of the factory above. 

Above Ground works needed to be coordinated precisely with the manufacturing of the precast components which were done in house as well. 

ABOUT.

AREA.

700,000 SQFT · 65,032 SQM

USES.

2 Buildings , one with a multi storey carpark podium with 8 floors of usable space. 2nd building is a heavy industrial manufacturing facility 